Folsom Middle School Portables

Folsom, California

Project Description:

​

This project comprised of site improvements to the Folsom Middle School Campus, including new AC paving, ADA upgrades and site signage. Selective structure and hardscape demolition was completed, followed by the relocation and installation of six portable classrooms and four new restrooms. The portable classrooms all received extensive interior and exterior upgrades including electrical, painting, casework, doors, carpeting, paneling, data and communication systems and new fire alarms.  

​

Project Value: $556,435

Start Date: 5/31/2018

Completion Date: 12/3/2018

Self-Perform: 33%

​